2021 Asphalt Street Rehabilitation

2021 Asphalt Street Rehabilitation
AS OF MARCH 31, 2022  - all work completed.
Oak Creek Drive and Ct.  completed
John Arden from Solon Rd to railroad tracks completed.

John Arden from E. University to Solon completed. 
Oak Creek culvert repairs completed. 
N. Rogers St. completed.
Lynn Ave completed.
W. Ross completed. 

Spencer / Odom St. completed.

The Asphalt Street Rehabilitation Program is an annual program that focuses on improving asphalt roads and streets in Waxahachie. The Public Works director reviews the condition of asphalt streets and determines the need for improvements.  Below is a list of some criteria that are utilized when adding streets to the program: 
-Visual inspection of the damage and condition
-Test drive the damage and condition
-Checks for traffic flow and speed limit
-Size of street
-Citizens requests

Once a street has been approved for the program, below is a general timeline of the phases of work:
Phase 1 - Excavation and Scarification of the old road
Phase 2 - Reshaping and Compacting the road with a stabilizer
Phase 3 - Asphalt Overlay

Please click here for the list of streets for the current year and previous years.